TRANSMISSION GAS PIPELINE FROM THE BULGARIAN-TURKISH BORDER TO STRANDZHA GAS METERING STATION

Contracting Authority:

Bulgartransgaz EAD

Location:
from Strandzha compressor station to the border with the Republic of Turkey

Period of implementation:
2018 – 2019

Glavbolgarstroy’s role in the project:
Prime contractor

Nature of works:

Investment design, construction and commissioning of the stage: DN1200 transmission line with a length of 11km from the Bulgarian-Turkish border to Strandzha gas metering station and a connection to the Transit gas pipelines TG1 and TG2.

prenosen-gazoprovod-km-