” National Oncology Hospital”, Bulgaria
Contracting Authority:
Ministry of Health-Care of the Republic of Bulgaria
Location:
Sofia, Bulgaria
Period of implementation:
August 2012 – November 2015
Glavbolgarstroy’s role in the project:
Expansion of a radiotherapy complex in the Clinic of Radiotherapy of National Oncology Hospital – EAD , Sofia
Nature of works:
New three-storey building, glazed warm connection to an existing building, renovation of the ground floor of an existing building.Executed monolithic construction, incl. 4pcs. bunkers for linear accelerators made of baritone concrete with a wall thickness of 100 cm to 185 cm, and a slab with a thickness of 170 cm to 200 cm. Finishing architectural and construction works, electrical installations, plumbing installations, HVAC installations, technological cold installations, external connections, vertical planning, road works and landscaping.
Technical characteristics:
Total built-up area: 4193.49m2
Built-up area: 2105.74m2