Waste Water Treatment Plant Rakovski

Contracting Authority:
Rakovski  Municipality

Location:
Rakovski, Bulgaria

Period of implementation:
January 2013– June 2014

Glavbolgarstroy’s role in the project:
Chief designer and “turnkey” contractor of the site

Nature of works:

Design and Construction of Waste Water Treatment Plant and road, water and sewer infrastructure to the WWTP, supply and installation of plant and equipment, personnel training and tests.

 

 

PSOV 2