Lions’ Bridge

Contracting Authority
Sofia Municipality
Location

Sofia, Bulgaria

Period of implementation
March 2013 – March 2015
Glavbolgarstroy’s role in the project
Prime contractor
Nature of works
  • Drawing up an investment project (phase – work project);
  • Reconstruction of the existing crossroad by construction of a new three – levels transport hub for three types of transport – motor, tram and metro;
  • Execution of structures: two direct roadways tunnels and two roundabout bridges;
  • Reconstruction of engineering infrastructure: including sewer, water pipe system, heating system, reconstruction of single-flow cables, reconstruction of overhead system, electricity supply system, telecommunications;
  • Road works at size load 11.5 t/axis of the road surface, including reconstruction of tramway. Landscaping, including automated irrigation system;
  • Restoration, preservation, artistic and spectacular lighting of Lavov most and throughout its range.
  • Actions on coordination and approval of the work project with the specialized control authorities, exploitation companies and the consultant;
  • Receiving of Building permit;
  • Temporary construction;
  • Delivery of the necessary materials, equipment and furniture;
  • Construction-assembly works;
  • Single, complex and 72-hour tests;
  • Drawing up of diligent and executive documentation;