Project
Biovet Peshtera
Contracting Authority
BIOVET
Location
Peshtera, Bulgaria
Period of implementation
May 2017 – April 2019
Glavbolgarstroy’s role in the project
Prime contractor
Nature of works
5 separate projects:
- Plant for manufacture of pharmaceutical products and fodder supplements with 12 subprojects with a total build-up area of over 25 000 m2,
- Logistic center with a total built-up area of 8 500 m2,
- Electrical supstation 110 kV with a total built-up area of 1 580 m2,
- Installation for instant granulation with three subprojects with a total built-up area of 9 600 m2,
- Reconstruction of a hotel and
- Reconstruction of WWTP with 400 000 PE.