Project
By-Product Department of “Amilum Bulgaria”
Contracting Authority
“Amilum Bulgaria”
Location
Razgrad, Bulgaria
Period of implementation
October 2018 – April 2019
Glavbolgarstroy’s role in the project
Reinforced concrete structures
Nature of works
The implementation of the project includes two main stages: construction of a new department for by-products: dewatering and drying plant for gluten, construction of a transformer station and a 0.4kV distribution system; and a second stage of construction of a building for transformer substations, an electrical room and a building for power distribution 6 and 0,4 KV.
The plant for gluten is a combined structure with a height of 30 meters. The metal structure has a total weight of 400 tons and is built on a reinforced concrete foundation slab with a thickness of 1 meter, based on 116 drilled piles, dia 600 mm.
Technical characteristics
- Built-up area: 1847,90 sq.m.
- Built-in volume: 8592,70 cubic meters